How to Read the Matched Relationships in Deep-Hole Coring Model Documentation as a Connected Set

Date:2026-10-27 06:21:27Views:57

Equipment documentation for deep-hole coring projects often lists drilling depth, torque, rotation speed, clamping through-hole diameter, and winch rope capacity in separate columns. Each column can be understood on its own; the trouble comes from treating one column as the capability of the whole machine. For example, one may remember only the maximum drilling depth without noticing which coring diameter that figure corresponds to, or look only at the maximum torque without asking at which rotation-speed range it occurs. Whether the documentation is read properly depends on whether several groups of mutually constraining values can be considered together.

The following uses the public documentation of the CR1200I as an example to explain how several matched relationships should be read as a connected set. These are approaches for reading documentation and making selection judgments, not construction records for any specific project; whether they can actually be applied still has to be confirmed against the formation, downhole tools, and site organization.

Group 1: First identify the diameter to which a drilling-depth figure corresponds

The CR1200I documentation gives reference drilling depths of 1200 m for N size, 1600 m for B size, and 700 m for H size. The three figures are listed side by side, indicating that drilling depth is not a single fixed upper limit for the whole machine but a range that changes with the coring diameter. When reading, first determine which coring diameter the project plans to use, then check the value in that row; applying the 1600 m figure for B size to a hole cored to H size would lead to a biased judgment.

The operational requirement corresponding to this relationship is direct: deep orebody control holes and resource upgrade holes usually require continuous core, and once the diameter is determined, the drill rod series, casing, and collar tools are also fixed accordingly. What the documentation can support is a judgment of “reference drilling depth at a certain diameter”; what it cannot support is that “this depth can be drilled at any diameter.”

How to Read the Matched Relationships in Deep-Hole Coring Model Documentation as a Connected Set

Group 2: Inclined-hole angle enters the hole-depth judgment rather than standing alone in a separate row

This model supports drilling angles of 45°–90°. The angle column appears to be a layout parameter, but it actually affects drill-string loading: at the same hole depth, inclined holes and vertical holes differ in drill-string friction, pull resistance, and hole-deviation control. The documentation lists the angle range separately, so when reading it should be placed in the same condition table as the drilling-depth ranges, rather than determining hole depth first and adding the angle afterward.

For inclined orebodies, layered orebodies, and structurally controlled mineral systems, inclined holes can more effectively cut through the target zone, and this requirement is valid; however, how deep drilling can actually proceed stably at a given angle is not provided in the documentation as angle-specific drilling-depth ranges, so this is a part that needs to be confirmed with the manufacturer or judged based on on-site trials.

Group 3: Maximum torque and maximum rotation speed belong to different ranges

The documentation states a power-head maximum rotation speed of 1500 rpm and a maximum torque of 2200 N·m, and provides two gear ratios, 1:2.2 and 1:3.3. These two values should not be read as being achieved simultaneously: the high-speed range usually corresponds to lower torque, and the high-torque range corresponds to lower speed. The purpose of the gear ratios is to match different rotation-speed–torque combinations to different coring sizes and rock hardness.

In operational terms, when competent hard rock alternates with locally fractured zones, what needs adjustment is this combination, not simply whether the torque is large enough. The documentation can indicate which ranges are available; it cannot indicate which range should be selected for each formation. That is part of on-site adjustment based on return water, pump pressure, and penetration performance.

How to Read the Matched Relationships in Deep-Hole Coring Model Documentation as a Connected Set

Group 4: Clamping through-hole diameter determines whether the drill-string system can connect

The clamp has a through-hole diameter of 150 mm and is suitable for drill rod systems such as NQ, HQ, PQ, NTW, and HTW. This group of values must be read together with the coring diameters in Group 1: after the diameter is selected, whether the drill rods can pass through the clamp and whether there is sufficient margin for collar operations must be checked here. If the through-hole diameter does not match the drill rod series, the drilling-depth ranges above cannot be realized.

The documentation also specifies hydraulic clamping and a wooden-horse wedge-type self-weight anti-drop structure; this describes the clamping method. Its performance under specific hole depths and drill-string weights still needs to be confirmed according to the actual drill-string assembly.

Group 5: Winch rope capacity must be calculated together with the planned hole depth

The wireline winch has a rope capacity of 1200 m and a lifting speed of 116 m/min. In deep holes, wireline coring accounts for an increasing proportion of auxiliary time; rope capacity must first cover the planned hole depth with margin, while lifting speed affects the pace of inner-tube retrieval. One of these values governs “whether it is long enough,” and the other governs “how fast it is”; they cannot substitute for each other.

How to Read the Matched Relationships in Deep-Hole Coring Model Documentation as a Connected Set

The 1200 m rope capacity in the documentation is the same as the 1200 m reference drilling depth for N size. When reading, note that these are two independent parameters, and it cannot be inferred from this that they match exactly at any diameter; the planned hole depth, rope specifications, and downhole resistance together determine whether the actual margin is sufficient.

Other matched items that can be checked along the way

Documentation itemValueQuestion to address when reading
Feed force / pull force55 kN / 160 kNWhether there is margin for deep-hole tripping and tool recovery
Main pump / auxiliary pump300 L/min, 28 MPa / 120 L/min, 21 MPaWhether hydraulic response is stable when multiple actuators are under high load
Mud system150 L/min, 7 MPaConditions for cuttings transport, hole-wall stability, and lost-circulation treatment
EngineCummins 6BTAA5.9, 132 kWPower matching and on-site fuel and cooling conditions

Each of these columns can answer one question, but none constitutes an independent conclusion. For example, a relatively large pull-force value only indicates that there is margin in lifting capacity; whether operations in the hole are actually smooth also depends on drill rod wear, rope condition, and mud performance.

Items still requiring confirmation after reading the documentation

  • When a certain coring diameter is combined with a certain drilling angle, the actual depth at which stable drilling can be achieved is not given by angle in the documentation and needs to be verified with the manufacturer or judged according to on-site conditions.
  • Treatment plans for downhole complexities such as lost circulation, collapse, and hole narrowing are process configurations and cannot be directly derived from whole-machine parameters.
  • The specific selection of drilling tools, bits, and mud materials must be determined separately according to ore type and formation; the documentation only states that the machine parameters are the same.
  • For the integrated crawler structure, movement conditions between platforms at a specific mine site depend on road width, platform dimensions, and slope; the documentation does not provide these on-site data.

Reading these five groups of relationships as a connected set yields a set of conditions, not a single “maximum capability” figure. The CR1200I documentation is better suited to checking whether the chain of “planned diameter—planned hole depth—drilling angle—drill-string system—winch capacity” is self-consistent; if any link in the chain does not match, one should first return to the documentation and on-site conditions for re-verification before discussing whether the equipment is suitable.