Pre-Start Transport and Assembly Preparation for Deep Orebody Follow-Up Holes

Date:2026-10-28 06:00:56Views:36

After an orebody is preliminarily delineated through shallow and intermediate-depth drilling, follow-up holes often need to continue verifying the deposit at depth, yet the hole sites frequently fall on hillsides, in forest areas, or at locations without existing roads. At this point, the first question the crew faces is not "can the equipment drill to this depth" but whether the equipment can be broken down into suitable transport units and delivered to the hole site, which assembly steps are required after arrival to restore drilling, and whether the site has the space and lifting conditions to support those steps. Preparing in this order is more reliable than filling in conditions after startup.

First, clarify the three on-site issues to resolve before startup

The operational objective of a deep follow-up hole is relatively clear: obtain continuous core, determine whether mineralization extends to depth, whether structures are connected, and whether alteration zoning changes. The difficulty is concentrated in the entry stage.

  • Transport issue: moving the complete rig uphill requires a sufficiently wide road surface, which mountain roads and narrow paths often do not provide.
  • Assembly issue: after splitting, each module must have space and a sequence for placement, connection, and inspection at the collar.
  • Supporting issue: whether power, mud, water, drilling tools, and spare parts can be continuously supplied after assembly is complete.

These three issues usually occur in sequence: transport determines the form in which the equipment arrives, assembly determines how soon drilling can resume after arrival, and supporting conditions determine whether continuous operation is possible after resumption. The preparation sequence below follows this line.

Step 1: Organize entry by transport unit rather than complete rig weight

The CR1000P is a 1000-meter-class portable split fully hydraulic core drill rig. The reference module weights given in the materials are: power unit 180–260 kg, operating unit 145 kg, hydraulic oil unit (including oil) 160 kg, mud unit 95 kg, and total weight 1640 kg. These values indicate that the split configuration is not simply breaking the complete rig into a few pieces, but dividing the power, hydraulic, operating, and mud systems into separately transportable units.

Pre-Start Transport and Assembly Preparation for Deep Orebody Follow-Up Holes

The items to be confirmed before startup can be listed by unit:

Transport unitReference weightPreparation points
Power unit180–260 kgConfirm handling method, loading/unloading points, and fuel supply route
Hydraulic oil unit (including oil)160 kgConfirm anti-tipping protection during transport and contamination protection for connections
Operating unit145 kgConfirm the layout position of the control console relative to the collar
Mud unit95 kgConfirm the distance between mud materials and the mixing site

The weight table only indicates the approximate magnitude of individual modules. Actual handling must also be judged based on route gradient, turning radius, road surface bearing capacity, and whether intermediate stockpiling is needed along the way. The materials do not provide the external dimensions and lifting point information of each module; these should be verified item by item with the equipment supplier before startup, and lifting methods should not be arranged based solely on the weight table.

Step 2: Break down post-arrival assembly procedures into inspection items

After split equipment reaches the hole site, the workload does not disappear; it merely shifts from complete rig transport to the assembly stage. The materials explicitly require that after assembly, the hydraulic connections, chuck, and power head status be confirmed item by item. Pre-start assembly preparation can be understood as several groups of checks:

  • Hydraulic connections: the connection sequence of pipelines between units, connector cleanliness, and tightness.
  • Chuck: maximum clamping force 130 kN, through-hole capacity 54–127 mm; after assembly, confirm that operation matches the drill rod specification.
  • Power head: maximum torque 1100 N·m, maximum speed 1250 rpm; after assembly, confirm normal rotation before proceeding to the drilling step.
  • Feed system: feed stroke 1.8 m, thrust 67 kN, pull force 130 kN; confirm smooth operation throughout the stroke range.

It is recommended to proceed through these inspection items in the order of "hydraulic connection—clamping and rotation—feed stroke" rather than carrying out all items simultaneously. The assembly site should also reserve corresponding operating space to prevent modules from obstructing one another.

Pre-Start Transport and Assembly Preparation for Deep Orebody Follow-Up Holes

Step 3: Verify the drilling depth target against drilling tools and winch support

The planned depth of the follow-up hole determines the coring diameter and drill rod series. The reference drilling depths given in the CR1000P materials are BQ 1150 m, NQ 1000 m, and HQ 550 m, with drilling angles of 45°–90° and applicable drill rod lengths of 1 m or 1.5 m. Before startup, the design hole depth should first be mapped to the corresponding diameter tier, then the required quantities of drill rods, core barrels, and bits should be back-calculated.

The winch system uses 6 mm wire rope, with a rope capacity of 1200 m, empty drum lifting force of 14.5 kN, full drum lifting force of 6.9 kN, and lifting speed of 116 m/min. When the planned hole depth approaches 1000 m, the rope capacity must be calculated together with the hole depth, and wire rope fatigue, rope end fixation, and spooling conditions should be checked. The 130 kN pull force is an equipment capability parameter; whether actual tripping is smooth also depends on hole deviation control, circulation maintenance, and hole diameter reduction handling. The pull force cannot be directly treated as a solution to downhole incidents.

Step 4: On-site preparation of power, mud, and consumables

There are two power options: diesel engine power requirement ≥132 kW, with Kubota, Cummins, Yunnei, or Yuchai optional; or a 30 kW × 3 electric motor configuration. Hole sites far from the grid are usually prepared with the diesel option, requiring advance planning of fuel storage and supply routes; platforms with stable power supply can evaluate the electric option, but grid capacity and cable layout conditions must be confirmed. The materials do not provide specific fuel consumption and power consumption data for the two options; cost comparison requires separate verification.

For mud, the mud pump flow rate is 100 L/min at 7 MPa, and the agitator speed is 1500 rpm with a mixing capacity of 1.2 m³/min. In deep hole sections, cuttings transport distance is long and circulation resistance is high. Before startup, sufficient mud materials should be prepared, and the direction of mud system adjustment should be determined in advance according to expected lost circulation zones, water-bearing fractures, and fault zones. The hydraulic system main pump has a flow rate of 200 L/min at 25 MPa, and the main oil tank is 200 L. For long-cycle operations, schedules should also be arranged for hydraulic oil contamination checks, filter replacement, and radiator cleaning.

Pre-Start Transport and Assembly Preparation for Deep Orebody Follow-Up Holes

Consumables preparation can be listed according to the actual consumption of deep hole construction: drill rods, core barrels, bits, wire rope, mud materials, and spare parts required for remote projects. The materials specifically note that for remote projects, preventive maintenance is more important than waiting for parts after a failure; this should be reflected in the preparation of the spare parts list.

Applicable boundaries and matters still requiring on-site confirmation

The value of the split configuration lies in reducing the deep hole project's dependence on large roads, but it does not mean the equipment can enter any mountain hole site. The following points are not covered by the materials and need separate confirmation before startup:

  • The external dimensions, lifting points, and allowable tilted handling angles of each module.
  • The gradient, width, turning radius, and road surface bearing capacity of the transport route.
  • Whether the collar platform area is sufficient for module placement, assembly, and drilling tool turnover.
  • The organization method and staffing for on-site lifting or manual handling.
  • The practical feasibility of laying out the designed drilling angle on a limited platform.
  • The fuel supply cycle for the power option or the grid connection conditions.

In addition, the materials state that final drilling efficiency, drilling depth, and core recovery results are subject to on-site working conditions. Geological conditions, downhole tools, drilling angles, and operating methods differ, and the actual performance of deep follow-up holes will also vary. Pre-start preparation should incorporate these variables into the plan rather than treating the reference drilling depths in the materials as guaranteed values achievable for every hole.