Pre-Start Inspection Checklist for Deep Well Water Supply Projects by Process Sequence

Date:2026-10-30 06:00:50Views:40

Pre-construction preparation for deep well water supply projects is often reduced to an equipment list: rig on site, air compressor on site, drilling tools on site, and work can start. But in actual execution, problems often arise outside the list—space for raising the mast was not reserved, air compressor displacement does not match hole diameter and depth, no hole stabilization plan exists for upper loose layers, and well casing and screen pipes for completion have not been decided. These items are scattered across different processes and can only be arranged as inspection items in the order of drilling commencement to avoid omissions.

Below, in three sections—before drilling, during drilling, and before well completion—the capabilities and support requirements in the publicly available RC500E information are mapped item by item to specific processes.

Before drilling: site, transport, and overall machine condition

This section addresses whether the equipment can smoothly enter the site, raise the mast, and be positioned. The RC500E has an overall weight of approximately 12 T, a crawler travel speed of approximately 2.5 km/h, and a reference climbing ability of 30°. Transport dimensions are approximately 6300×2100×2500 mm, and working dimensions are approximately 4000×2900×6800 mm. The inspection items corresponding to these data are:

  • Whether the bearing capacity and width of the access road can accommodate crawler travel and transport vehicle passage; move cautiously in soft soil and wet, slippery areas;
  • Whether the transport vehicle's load capacity and securing points match the approximately 12 T overall machine, and whether height restrictions along the route affect transport;
  • Whether working space and a safe operating area required for raising the mast are reserved around the hole position.

At the same time, daily pre-work routine inspections should cover high-pressure air hoses, joints, safety ropes, rotary head, crawlers, mast, and hydraulic system. This machine uses 132 kW diesel power with a rated speed of 2400 r/min, offering better independent operation capability at remote sites lacking a stable power supply, but long-term high-load operation requires attention to engine cooling, air filtration, and the fuel system. This part corresponds to power assurance, not drilling capability itself.

Pre-Start Inspection Checklist for Deep Well Water Supply Projects by Process Sequence

Air supply and drilling tools: configure support based on hole depth, hole diameter, and formation

Air-lift reverse circulation uses compressed air to establish return flow in the inner pipe, carrying cuttings from the hole bottom back to the surface through the inside of the drill pipe. The RC500E recommends a working air pressure of 1.7–3.5 MPa and an air consumption of 17–42 m³/min. As hole depth increases, hole diameter enlarges, rock layers harden, or construction altitude rises, the required displacement increases. Therefore, pre-drilling air supply checks are not just "whether the air compressor has arrived," but:

  • Whether the planned air compressor's discharge capacity can cover the cuttings return demand under the planned hole diameter and depth;
  • Whether the DTH hammer and reverse circulation cuttings return share the same air supply conditions;
  • Whether accessories such as high-pressure air hoses and oil mist lubricators are provided according to pneumatic system requirements.

Regarding drilling tools, this machine has a drilling diameter of 140–400 mm, a maximum drilling depth of 500 m, can be equipped with a 3.3 m or 6.6 m feed stroke, and supports 1.5/2/3/6 m drill pipes. The selection of feed stroke and drill pipe length should be determined together with transport conditions, hole position space, and the main drill pipe length, and cannot be decided solely by the goal of "fewer pipe connections."

Formation changes: prepare separately for upper overburden and hard rock sections

In-hole processes for deep well water supply are usually handled in two sections. The difficulty in weathered rock and upper loose overburden lies in hole wall stability. The information recommends first using casing, mud, or other hole stabilization methods to establish a stable hole section before entering more intact rock formations for pneumatic reverse circulation drilling. After entering more intact rock formations such as granite, basalt, and limestone, DTH hammer impact, rotation speed, feed force, and air volume need to be coordinated and matched; if cuttings removal is poor, continuing to increase thrust may exacerbate bit wear and sticking risk.

Pre-Start Inspection Checklist for Deep Well Water Supply Projects by Process Sequence

Faults, fractured zones, and open fissure formations bring another set of problems: block falling, hole shrinkage, air leakage, and sticking. The information's recommended approach is to reduce thrust speed, maintain continuous hole cleaning, and use casing or foam assistance depending on hole wall stability. When air leakage is severe, merely increasing pressure without sufficient displacement may still fail to provide effective airflow at the hole bottom; both displacement and process must be addressed. These are dynamic judgments during drilling; what can be done before starting is to incorporate casing, foam systems, and other support into the plan rather than adding them after problems arise.

Before well completion: aquifer records and well casing and screen preparation

After the borehole enters the main aquifer, groundwater will change the cuttings return and DTH hammer working state in the hole. At this step, record the depth of the main water-producing layers and adjust air supply, hole cleaning, and casing methods according to water inflow. In the well completion stage, arrange screen pipes and water-stop sections according to aquifer positions to ensure long-term pumping performance. The 140–400 mm hole diameter range allows different well diameters to be designed according to well casing size, submersible pump, and expected water output, but the final well depth should still be determined by hydrogeological data and the actual water-producing layers; equipment capability only provides depth margin and does not replace water-finding judgment.

For lifting and rotation, 300 kN lifting force, 150 kN feed force, and 8000–12000 N·m rotation torque provide operating margin for tripping, casing handling, and drilling in hard rock sections. When abnormal resistance is encountered, the hole should be cleaned first and the in-hole condition assessed; it is not advisable to directly use maximum lifting force to pull forcefully.

Pre-Start Inspection Checklist for Deep Well Water Supply Projects by Process Sequence

Support equipment and items to be confirmed

A complete construction system also requires project-specific selection of reverse circulation DTH hammers, bits, drill pipes of different specifications, casing tools, air compressors, high-pressure air hoses, oil mist lubricators, foam pumps, and generators, etc.; not all need to be configured. The 20 kN auxiliary winch can be used for handling DTH hammers, drill pipes, and casing tools, and the rated load should be controlled during use.

The following items are not concluded in the information and need separate confirmation at the project level: the actual drillability of specific formations, the final water-producing layer position corresponding to the planned well depth, local requirements for well completion materials and water-stop processes, and the actual matching parameters between the air compressor and DTH hammer. Without these conditions confirmed, equipment parameters alone cannot determine whether the project can achieve the expected well completion.