Applicable Conditions and Items Still to Be Verified for Slope Photovoltaic Construction

Date:2026-10-30 07:44:23Views:54

When installing photovoltaic piles on slopes, the trouble is often not whether drilling can be done, but whether the equipment can stop stably and whether the drill bit can align with the pile position. On slopes with left-right height differences and undulating ground between piles, fixed-height crawler equipment often requires an excavator or manual labor to first level a section of the site, then move the machine, then align the hole. For an array of dozens of pile positions, the number of leveling and machine-moving operations adds up, and the cycle is fragmented. What really needs to be judged is: under slope conditions, which adjustment capabilities can reduce such repetitive actions, and which conditions must still be ensured by site preparation and safety measures.

Actual Constraints of Slope Photovoltaic Pile Foundation Construction

Mountainous and hilly photovoltaic sites share several common conditions: the site extends along the slope, and left-right height differences may exist even between pile positions in the same row; construction access roads are generally poor, and equipment entry and on-site transfer are restricted; pile positions are densely arranged in arrays, and each pile position requires positioning, hole alignment, and drilling. Holes for photovoltaic support foundations are usually shallow, with drilling depth of 0–6 m and hole diameter of 80–600 mm according to the data, representing high-frequency shallow foundation work rather than deep hole drilling.

When these conditions are combined, the equipment faces two test questions: first, whether a usable construction posture can be obtained on uneven ground; second, whether hole alignment can be completed after stopping stably without significantly moving the machine.

Breaking Down Slope Problems into Posture and Hole Alignment

"Slope adaptability" is a general term, which roughly divides into two parts in terms of work procedure. In terms of posture, the equipment needs to maintain the relative relationship between the chassis and the drill mast on uneven ground so that the drill rod can enter the pile position at the design angle; in terms of hole alignment, after the chassis stops stably, the drilling work mechanism needs lateral and front-back fine adjustment room to avoid moving the entire machine again for a deviation of tens of centimeters.

Applicable Conditions and Items Still to Be Verified for Slope Photovoltaic Construction

If both parts are solved by repeated leveling and machine moving, construction organization will revolve around excavators and manual labor; if the equipment itself has corresponding adjustment structures, the frequency of leveling and machine moving may decrease. However, adjustment capability itself does not equal safety margin, nor does it mean any slope can be directly accessed for construction. This point will be addressed separately later.

Several Structures in PV390H Data Corresponding to Slope Requirements

Crawler Height Adjustment

The PV390H crawler height telescopic dimension is 1200 mm, and the height of the two side crawlers can be adjusted according to slope height differences, used to handle more obvious left-right height differences. The data describes it as suitable for photovoltaic projects on hillsides, hills, and areas with obvious undulations. In terms of work procedure, this type of structure changes the initial posture of the equipment on the slope, reducing dependence on "leveling before every pile position."

It should be noted that the data also clearly states: the high-low leg function can improve slope adaptability, but cannot replace safety construction platforms and foundation bearing capacity assessment. In other words, adjustable crawler height is a posture adjustment method, not a slope access permit.

Mast Pitch and Left-Right Swing Arms

The mast pitch range is 120°, and the drilling posture can be adjusted according to terrain and pile position requirements; the mast uses dual-cylinder left-right swing arms, allowing lateral fine adjustment after the chassis stops stably. For array-arranged photovoltaic stations, lateral fine adjustment corresponds to the hole alignment requirement of "whether the pile position is to the left or right," reducing frequent small-range chassis movement.

Applicable Conditions and Items Still to Be Verified for Slope Photovoltaic Construction

Telescopic Compensation

The equipment has 450 mm telescopic compensation, used for fine adjustment in the front-back direction of the drilling work mechanism. The front-back direction is also a source of deviation on slopes; crawler stopping positions cannot be precise every time. Telescopic compensation, combined with swing arms and pitch, constitutes the multi-directional pile position alignment capability described in the data.

Drilling Capability Must First Cover Pile Type, Then Posture

Posture adjustment addresses "whether the machine can stop stably and align the hole," while drilling capability addresses "whether the hole can be formed after alignment." The PV390H data gives a drilling diameter of 80–600 mm, drilling depth of 0–6 m, reducer torque of 13000 N·m, drill rod speed of 100 r/min, chain pressurization, and power from a 130 kW Yuchai six-cylinder turbocharged engine. These data correspond to shallow photovoltaic foundation pre-drilling: the hole diameter is selected according to the support foundation design, the depth is determined by the pile type, and larger hole diameters and dense soil layers impose higher requirements on rotary torque.

It should be noted that the final hole diameter and hole depth should be based on project design drawings and construction technology; the data parameters do not constitute a conclusion on hole-forming quality for specific projects. When encountering cobblestones, backfill layers, and strongly weathered rock, the data recommends controlling penetration speed according to rotary load to avoid excessive downward pressure causing hole deviation or drill sticking.

Boundaries Regarding Strata and Configuration

  • Soil layers and loess are usually more suitable for photovoltaic foundation drilling, but moisture content and density affect hole wall stability; loess slopes may experience reduced adhesion after rain, and crawler ground contact conditions should be monitored simultaneously.
  • Highly plastic clay easily clogs the drill, requiring adjustment of rotation and penetration according to drill bit load and timely lifting of the drill for cleaning.
  • Cobblestone sand, gravel, and mixed overburden layers have large particle variations, which may cause drill bit bouncing, hole deviation, and local sticking; drilling tool selection and penetration method should be arranged separately.
  • Backfill waste layers may contain bricks, concrete blocks, rebar, and voids; when abnormal impact or rotary sticking occurs, the machine should be stopped for inspection.
  • The data states that after replacing with impact drilling tools, it can be used for strongly weathered rock and rock layers, but does not give impact hammer models and impact energy; hard rock efficiency should not be inferred from this.

The crawler shoe width is 300 mm, suitable for dirt roads, grassland, gravel ground, and general slopes; however, on wet slippery slopes, soft soil, and areas with large cross slopes, the data requires reducing speed and paying attention to rollover risk. A winch can be added for assistance on steeper slopes, but anchor points, wire ropes, and traction direction must be confirmed reliable, and the winch cannot replace construction roads and safety platforms.

Applicable Conditions and Items Still to Be Verified for Slope Photovoltaic Construction

Conditions Under Which This Solution Deserves Inclusion in Comparison

If the project meets the following conditions, a high-low leg hydraulic photovoltaic pile driver such as the PV390H deserves inclusion in equipment comparison: the site is located in mountains or hills, with obvious left-right height differences between pile positions; the pile type is shallow photovoltaic support foundation, with hole depth in the 0–6 m range and hole diameter in the 80–600 mm range; pile positions are densely arrayed, and it is desired to reduce work procedure interruptions caused by whole-machine movement and repeated leveling; the strata are mainly soil, loess, clay, and mixed overburden, with hard rock sections considered separately for drilling tools and technology.

If the site is mainly flat, pile positions are sparse, or slope conditions exceed the range covered by equipment posture adjustment, the value brought by the high-low leg structure needs to be re-evaluated.

Items Still to Be Verified

  • On-site slope and cross-slope conditions, crawler ground contact pressure, and foundation bearing capacity need to be confirmed by the project owner and safety assessment; the data does not provide a slope access permit conclusion.
  • Construction platforms, access roads, and drainage measures need separate design; changes in adhesion on loess slopes after rain should be included in on-site management.
  • Winch configuration, anchoring scheme, and traction direction need to be verified with the supplier and on-site safety responsible person.
  • The data does not give impact drilling tool models, impact energy, and actual efficiency for hard rock sections, which need separate confirmation according to project strata.
  • Actual drilling efficiency, hole-forming quality, and passability are affected by geology, slope, drilling tools, pile type, and operation method, and should be based on on-site working conditions and project foundation design.

Model naming clarification: the original data name is "high-low leg hydraulic photovoltaic pile driver"; to be consistent with the PV390 and PV390R series, this version is recorded as PV390H, with H used to distinguish the high-low leg/crawler height adjustable version; values such as engine, hole diameter, drilling depth, torque, and adjustment dimensions are retained as in the original data without modification.