When drilling a water well beside a village road, what is most often underestimated before work begins is not the drilling rig itself, but the pace at which the site and supporting materials are put in place. Well locations are often chosen at the roadside, next to a courtyard, or at the edge of a field, leaving limited space to position equipment; village access roads vary in width and load-bearing capacity; and power supply, air supply, water source, and well-completion materials each fall under different work packages. If the main machine is brought in first and these conditions are addressed afterward, equipment often sits idle waiting for the air compressor, casing, or bearing pads. The following sections follow the drilling sequence to outline the order in which the site and supporting materials should be secured before work begins on such projects, and use publicly available WR260 information to explain which equipment features correspond to these conditions and which items still require on-site verification.
1. First determine the well location and site: the equipment must fit and be stably supported
The first constraint for a well location beside a village road is the site. After the wellhead position is determined, space must be reserved around the wellhead for the main machine to park, the mast to be raised, drill pipes to be run and pulled, and personnel to pass. The WR260 has overall dimensions of approximately 3900×1750×2250 mm and an overall weight of 5.7 T. It is a compact crawler water well drilling rig and is easier to move into industrial sites and space-constrained construction areas than large deep-water-well drilling rigs. However, this does not mean drilling can begin directly beside any village road; raising the mast and tripping in and out still require a certain operating clearance, and the specific space required should be based on formal technical documentation and the site layout.
Ground bearing conditions must also be checked in advance. On soft soil, backfill, or sites after recent rain, the outriggers can sink, so bearing pads need to be prepared. The WR260 has an outrigger stroke of 1.4 m, allowing the equipment to be supported and leveled on mildly uneven ground; before opening the hole, the whole machine should be stable, and additional bearing pads are needed on soft ground to prevent outrigger settlement from causing the mast to tilt and the hole position to shift. Therefore, in the site preparation checklist, bearing pads, leveling tools, and drainage measures should be secured before the main machine arrives, rather than handled ad hoc after the equipment is on site.
2. Access route: village road width, turns, and load-bearing capacity must be checked in advance
When the equipment travels on its own tracks, the speed is about 2.5 km/h, with a reference maximum gradeability of 30°. Village roads, field roads, and gravel sites are scenarios for which the steel crawler chassis is well suited, but before relocating, the mast should be retracted and slope and ground bearing conditions assessed. What needs to be verified is not only road width but also turning radius, bridge and culvert load-bearing capacity, roadside overhead lines, tree branches, and other obstacles. If part of the village road is narrow or the roadbed is soft, the access route may need to be assessed in sections, and local treatment may be required before arranging equipment travel.

This step runs in parallel with the transport of supporting materials: if drill pipes, casing, filter media, and the air compressor are delivered by other vehicles, they are likewise constrained by village road conditions. Putting equipment access and material transport on the same route verification checklist helps avoid the situation where the main machine arrives but material vehicles cannot get in.
3. Power and air supply: determine the process first, then the supporting equipment
The air supply conditions for water well construction depend on the drilling method. The WR260 mainly uses DTH hammer drilling, and the reference working air pressure given in the documentation is 1.7–2.5 MPa with an air consumption of 17–31 m³/min. Insufficient air compressor displacement will cause inadequate DTH hammer impact and difficult cuttings removal; when the hole diameter increases, the rock formation hardens, or the altitude rises, a more adequate air flow is usually required. Therefore, before work begins, the design hole diameter, expected rock formation, and air compressor displacement should be checked together, rather than waiting until arriving on site.
For power, the WR260 is equipped with a 76 kW diesel engine, and the documentation also provides an optional electric motor power solution. For industrial sites, mines, or fixed construction projects with stable power supply conditions, electric motor power can be considered to reduce diesel replenishment and exhaust issues; the final motor power, voltage, and control method should be based on the formal configuration. If there is no stable power grid at a well location beside a village road, diesel power and fuel reserves must be arranged in advance, and the fuel storage location should also be included in the site layout.
4. Drilling tools and well-completion materials: equip according to hole depth and hole diameter
The WR260 has a maximum drilling depth of 260 m, a drilling diameter of 140–305 mm, a rotary torque of 4000–5300 N·m, and a rotary speed of 45–70 r/min. It is suitable for drilling with 76 mm or 89 mm drill pipes and common DTH hammers. The single feed length is 3.3 m, which can match 1.5 m, 2 m, and 3 m drill pipes. Before work begins, the drill pipe specifications, quantity, and spare quantity should be clarified according to the design well depth and drilling structure, and the matching relationship of downhole tools such as the DTH hammer and bit should also be confirmed.

Well-completion materials should be arranged before drilling begins. The documentation clearly states that before well completion, the well depth, well diameter, filter pipe, and sealing intervals should be determined based on the aquifer position, expected water yield, and local water quality requirements. Well casing, filter pipes, filter media, and water-stop materials are key materials for the well-completion stage. Sites beside village roads are limited, so material storage locations and the sequence of phased deliveries need to be planned in advance to avoid competing for site space with drilling tools and the air compressor.
5. Formation contingency plan: prepare separately for the upper overburden and hard rock sections
The WR260 documentation sets relatively clear boundaries for formation conditions: directly using a DTH hammer in soil, clay, sand, and gravel overburden may cause hole collapse and buried drilling tools. Casing, mud, or other hole-stabilizing processes should be selected according to the formation, establishing a stable hole opening and upper hole section first, and then entering the rock formation for pneumatic DTH drilling. Weathered rock formations are prone to wall sloughing and hole shrinkage; broken zones and fractured formations are prone to block falling, air leakage, and stuck drilling; limestone karst caves and open fractures may make it difficult to effectively transmit air compressor pressure and flow to the hole bottom.
Therefore, material preparation before work begins cannot be based only on the single case of "drilling rock formations." Whether casing, mud materials, or foam assistance need to be available on site depends on the judgment of the upper overburden and possible broken zones. These judgments require support from local hydrogeological data and preliminary site surveys and cannot be determined solely from drilling rig parameters.

6. Supporting and safety conditions: winch, hole cleaning, and site organization
The WR260 is equipped with a 1.5 T auxiliary winch, which can be used to handle DTH hammers, drill pipes, casing tools, and some on-site auxiliary equipment. Using the winch can reduce the intensity of manual handling, but the load should be controlled during lifting, and personnel should be kept from standing under suspended loads. When relocating frequently, the tracks and loading tie-down points should be checked; before daily construction, the engine, hydraulic system, rotary head, mast, winch, and high-pressure air hoses should be checked. These inspection items are routine construction and maintenance requirements and should be made into a written checklist before work begins.
The documentation also mentions a 2.73 m parameter labeled "Loading width / Width of loading," which is inconsistent with the overall external width of 1750 mm. This article does not interpret it as the actual transport width; for loading and transport dimensions, formal production technical documentation should be used for confirmation.
7. Items still requiring confirmation from the manufacturer or on site
- Whether the specific section of the village road can bear the 5.7 T whole machine and transport vehicles, and whether bridges, culverts, turns, and overhead clearance are adequate;
- The operating clearance required around the well location for raising the mast and tripping in and out, and the bearing pad plan for soft ground;
- Under the design hole diameter and rock formation conditions, whether the air compressor displacement falls within the reference range of 17–31 m³/min, and how altitude effects should be corrected;
- The hole-stabilizing process for the upper overburden and the specific quantities of casing and mud materials;
- The design parameters of the well casing, filter pipe, filter media, and water-stop structure for well completion;
- The actual meaning of the "Width of loading" item of 2.73 m and the transport dimensions.
Only by laying out these conditions in the order of "site—route—power and air supply—drilling tools and materials—formation contingency plan—daily inspection" can equipment selection have a basis. The WR260's compact dimensions, crawler chassis, 1.4 m outrigger stroke, 3.3 m feed length, and 15 T lifting force correspond respectively to the needs of limited space beside village roads, ground leveling, pipe connection rhythm, and drilling tool handling; however, whether it is suitable for a specific well location still depends on the results of verifying the above conditions item by item, and conclusions cannot be drawn solely from drilling depth or any single parameter.