Preparations for spudding a deep water supply well are not the same checklist as for a 200–300 m shallow well. Once hole depth reaches 700–800 m or even the 1,000 m class, drill pipe weight, casing weight, air compressor output, and drilling site footprint all scale up. Any item left to be addressed on site can bring the entire operation to a halt. This article lists conditions in deep water supply projects that are easily deferred, in the order of "what to confirm before spudding," and uses verified information on the WRT1000, a 1,000 m class truck-mounted direct tower water well rig, to explain which conditions are directly related to equipment capability and which must be secured separately by the project owner.
First, a clarification: the following is not a construction record of a specific project, nor does it imply that this model has completed a certain type of well in a certain location. The listed conditions are verification directions at the planning level; actual decisions must still be made in conjunction with hydrogeological design and confirmed with the manufacturer.
Before Entry: Convert Equipment Dimensions into Road Conditions
The first hurdle in deep well projects is often not downhole but whether the equipment can reach the hole location. The WRT1000 has an overall weight of approximately 26 T and transport dimensions of approximately 10.8 × 2.5 × 4.23 m. The advantage of the truck-mounted chassis is that it can move between hole locations on its own, reducing repeated loading and unloading onto flatbed trucks. However, a transport height of 4.23 m means the entry route must be checked in advance for height restrictions. Items to verify include:
- Clearance height of bridges, tunnels, overhead lines, and factory gates along the route, and whether there is margin;
- Width, turning radius, and gradient of village roads, field roads, and mining area access roads, and whether they can accommodate a 2.5 m wide vehicle body;
- Whether there is open space near the hole location for turning around or reversing in, and whether the mast of the truck-mounted direct tower rig needs to be restored to position during transport;
- Load-bearing capacity of soft-ground sections and temporary access roads after rain, and whether they may cause the vehicle to get stuck or require prior treatment.
These conditions are unrelated to the rig's own capability but directly determine start-up time. The data only provides overall weight and transport dimensions; specific axle load distribution, minimum turning radius, and similar data are not provided in this article's source material. Before entry, request chassis parameters from the manufacturer and confirm separately with the carrier and road authority.

Drilling Platform: Allow Margin for Load and Layout under Deep Hole Conditions
At 1,000 m class depths, the drilling site must accommodate more equipment and materials: the main rig, air compressor, mud system, drill pipe, casing, and the drill tools and air hoses handled by auxiliary winches. The WRT1000 is equipped with a 4 T large auxiliary winch and a 3 T small auxiliary winch for moving DTH hammers, drill pipe, casing, air hoses, and site accessories. This reduces manual handling, but winch lifting also requires corresponding placement areas and working radii on the platform.
Before spudding, it is recommended to confirm: whether the platform area is sufficient to store drill pipe and casing without obstructing tripping channels; whether the foundation has been treated to withstand the concentrated load of the 26 T rig plus drill tools; whether the mud pit, settling pit, and drainage ditches are located away from the wellhead and meet on-site environmental requirements; and whether space is reserved for lighting and power generation for night operations. The source material does not provide ground bearing pressure or outrigger reaction forces; platform load design must be calculated by the on-site civil contractor and should not be estimated simply from overall weight.
Process Route: Determine Hole Diameter and Formation First, Then Work Back to Support Equipment
Public information on the WRT1000 shows a drilling diameter of 105–800 mm, maximum drilling depth of 1,000 m, 51/52 T lifting force, 11 T axial pressure, rotation in dual modes of 20,000/10,000 N·m corresponding to 70/140 r/min, feed stroke of 7 m, compatibility with 3 m or 6 m drill pipe, and recommended drill pipe diameter of 114 mm. Before spudding, these figures help judge how far support equipment must be prepared, rather than being used to directly set the plan.
| Confirmation Item | Data Basis | What to Secure on Site |
|---|---|---|
| Target hole diameter and depth | Hole diameter 105–800 mm, maximum depth 1,000 m | Determine diameter based on water yield, well casing, and pump type; larger diameters simultaneously increase drill tool load, casing weight, and air compressor demand |
| Drill pipe specification | 3 m or 6 m drill pipe available, recommended diameter 114 mm | 6 m pipe reduces joint make-up frequency; 3 m pipe suits sites with space or transport constraints |
| Lifting and tripping | 51/52 T lifting force | Calculate whether the weight of drill pipe plus casing at the deepest section falls within capacity |
| Upper formation hole stability | Soil, clay, sand, and gravel layers can be handled by mud rotary, casing, etc. | Determine mud materials, casing specifications, and casing running sequence |
| Hard rock drilling | Intact hard rock can use medium-to-high pressure DTH hammer, recommended air pressure 1.65–8 MPa, air consumption 16–96 m³/min | Select air compressor based on DTH hammer specification, hole diameter, depth, altitude, and rock hardness |
The most easily underestimated item in this table is the air compressor. 1.65–8 MPa and 16–96 m³/min are the equipment's compatibility range, not a guarantee that any air compressor will suffice. Actual projects must calculate continuous air supply capacity based on DTH hammer model, hole depth, and altitude, and confirm whether the site can accommodate equipment of the corresponding output along with air storage and piping systems. The source material also notes that as hole diameter increases, air compressor demand rises accordingly; these two items should be confirmed together.

Well Completion: Casing, Screen, and Aquifer Data Cannot Wait Until Drilling Is Finished
If hydrogeological data for a deep well is supplemented only after spudding, it is often too late to adjust hole diameter and casing plans. Before spudding, obtain the target aquifer depth, expected water inflow, and preliminary water quality assessment, and use these to determine screen position, sealing sections, and pump type. The WRT1000 source material notes that after entering the main aquifer, increased water in the hole affects DTH hammer cuttings discharge and circulation status; the depth of main water-producing zones should be recorded during construction, and air supply, hole cleaning, and casing plans adjusted accordingly. This means the site needs a mechanism for recording and judgment, not just completing the hole.
Casing weight and running method are another point to verify in advance. The source material mentions that the equipment has partial casing operation capability but does not provide specific casing running specifications and depth limits. The project owner should, based on design hole diameter and casing weight, confirm with the manufacturer the method for running and pulling casing, whether auxiliary equipment is needed, and whether lifting force has margin when running casing at the deepest section.
Remote and Water-Scarce Sites: Air Drilling Is Conditional, Not Unconditional
The source material notes that in suitable formations, pneumatic DTH drilling has lower dependence on large volumes of mud water and can be used in arid mining areas, remote agricultural sites, and water-scarce construction points. This is a practically meaningful orientation for deep water supply projects, but the prerequisites are that the formation suits air drilling, the air compressor package is in place, and the site can organize corresponding air supply and cuttings discharge. Upper loose overburden, weathered rock, and fractured zones still require mud or casing for hole stability; it cannot be assumed before spudding that the entire hole can use air drilling.

Remote projects must also confirm fuel supply, spare parts availability, and maintenance conditions. The equipment is powered by a 194 kW diesel engine; long-term deep hole construction places higher demands on cooling, air filtration, and fuel system maintenance, and dusty sites require more frequent cleaning of filter elements and radiators. These are operating conditions; specific maintenance intervals should follow the manufacturer's instructions.
Items Not Covered by the Data: Ask Clearly During Inquiry
The above verification items are based on public information for this model; some stages lack direct data. For formal inquiries, it is recommended to submit the following information together and request written confirmation from the manufacturer:
- Target well depth, hole diameter and well structure for each section, and whether large-diameter sections are included;
- Stratigraphic column description: overburden thickness, lithology, fractured zones, and main aquifer positions;
- Planned drilling method (mud rotary, pneumatic DTH hammer, or staged combination) and corresponding air compressor parameters;
- Casing specifications, running depth, and well completion method;
- Entry road height restrictions, width, gradient, and platform load capacity, as well as local requirements for drilling site layout;
- Fuel, water source, power supply, and distance to spare parts service;
- Technical data not listed in the source material, such as chassis axle load, outrigger reaction forces, and rig transport securing requirements.
Upfront confirmation for deep water supply projects is essentially about laying out possible downhole variations on the table in advance. Equipment capability defines the boundary; site conditions determine whether that boundary can actually be used. Assigning the above items to responsible persons before spudding is more controllable than returning to supplement conditions after problems arise downhole.