Pre-Drilling Checklist for Deep Well: Drill String and Site Verification

Date:2026-11-07 06:00:47Views:23

When a deep water well project enters the pre-drilling preparation stage, the most common problem is not insufficient equipment capability but a failure to align drill string, process, and site: drill pipe specifications do not match mast travel, resulting in more rod connections than expected; air compressor pressure meets the requirement but displacement is insufficient, making impact and cuttings removal difficult simultaneously in hard rock sections; and whole-machine weight and outrigger layout have not been checked against site bearing capacity, leaving a risk of settlement even after leveling. Below, using a 750 m-class telescopic-mast crawler water well rig as an example, the items worth checking one by one before spudding are laid out by drill string, process, and site.

First determine how deep the well will be drilled and what diameter to open

The rig has a maximum drilling depth of 750 m, a hole diameter of 105–450 mm, 176 kW power, 40 T lifting force, and 6 T axial pressure. Only by looking at these figures together can you judge whether the depth target falls within the rig's operating range: when the hole diameter is at the upper limit, rotation load, cuttings removal air volume, and drilling tool specifications all tighten simultaneously. Maximum drilling depth is a reference capability of the equipment, not a guarantee that 750 m can be reached in any formation; the target well depth should be determined by the water-bearing horizon identified from regional hydrogeological data, not back-calculated from the equipment's nominal value.

Items to check in the drill string column

The documentation recommends 102 mm drill pipe and supports direct operation with 6 m drill pipe and 6 m casing. At 750 m-class hole depths, the drill pipe bears its own weight, borehole wall friction, and rotational torque, so thread condition, straightness, and rotation scheduling need to be established before spudding. The telescopic mast can improve the whole-machine transport profile in the transport state, while in the working state it still supports 6 m drill pipe and casing operations, thereby reducing the number of rod connections.

Pre-Drilling Checklist for Deep Well: Drill String and Site Verification

Hoisting and rotation configuration choices

The rotation system has two configurations: 13000/6500 N·m or 15000/7500 N·m, with a maximum rotation speed of 95/190 r/min. Large-diameter, high-hard-rock-ratio, and high-friction hole sections rely more on torque reserve, while lower-resistance stages can use higher speeds. Which setting to choose should be determined by design hole diameter, drilling tool specifications, and the main rock formations, not by looking at just one figure. The 40 T lifting force is used for normal tripping, DTH hammer recovery, and some casing handling; when abnormal pulling resistance occurs, the downhole condition should be assessed first and addressed through hole cleaning and slow pulling, rather than treating maximum lifting force as a universal solution.

Fast actions and auxiliary winch

Fast lifting speed is 31 m/min and fast feed speed is 65 m/min, mainly used for drill pipe handling and power head return. For 750 m-class projects, single auxiliary times are not long, but with many rod connections the cumulative effect affects progress. The auxiliary winch has a 2.5 T lifting force and can be used for handling DTH hammers, drill pipes, and casing tools; rated load and lifting safety requirements must be observed during use.

Pre-Drilling Checklist for Deep Well: Drill String and Site Verification

Drilling process and air supply conditions must align

The rig's recommended working pressure is 1.6–6 MPa with air consumption of 16–75 m³/min, and it can match medium- and high-pressure DTH hammers. Under deep-hole and large-diameter conditions, air compressor displacement and pressure must both be satisfied: sufficient pressure with insufficient displacement can still result in inadequate impact and difficult cuttings removal. Upper soil layers, clay, sand layers, and gravel layers can use mud rotary drilling, with optional mud pumps, centrifugal pumps, generators, and foam pumps. In fractured zones, fissures, and air-leakage formations, feed should be reduced, hole cleaning maintained, and casing or foam assistance used as appropriate; when air volume loss is obvious, it should be determined whether large fissures exist rather than simply increasing pressure. After entering the main aquifer, the depth of the water-producing layer should be recorded, and air supply, hole cleaning, and casing methods adjusted accordingly.

Transport and site conditions cannot be left until mobilization

The whole machine weighs about 14 T, has overall dimensions of about 6.64 × 2.25 × 2.67 m, a travel speed of about 3 km/h, a maximum climbing angle reference of 21°, and a hydraulic outrigger stroke of 1.6 m. Before cross-project transport, confirm flatbed load capacity, road width and height limits, and tie-down points; the telescopic mast must be in a reliably locked state, and 6 m drill pipe and casing must be secured separately. On site, deep-hole construction takes a long time, and the mast bears drill string and rotation loads over the long term, so equipment levelness and outrigger settlement control are critical; soft ground should use pads of sufficient area; travel risks in soft soil, slopes, and wet slippery areas must be strictly controlled.

Pre-Drilling Checklist for Deep Well: Drill String and Site Verification

Pre-drilling item-by-item checklist

Check itemContent to confirmBasis or to be verified
Well depth and diameterWhether the target water-bearing horizon and design hole diameter are within the 105–450 mm rangeThe equipment's maximum drilling depth of 750 m is a reference capability; actual hole-making is constrained by formation
Drill string102 mm drill pipe specifications, 6 m length, thread and straightness inspection scheduleDocumentation-recommended configuration; specific procurement specifications must be checked with the drilling tool supplier
Rotation settingSelect 13000/6500 N·m or 15000/7500 N·m based on hole diameter, rock formation, and drilling toolsMust be judged in conjunction with the main rock formations and design hole diameter
Air supply matchingWhether air compressor pressure and displacement can simultaneously cover 1.6–6 MPa and 16–75 m³/minActual selection must be calculated according to DTH hammer model and hole depth
Wall protection and cuttings removalMud scheme for upper overburden, casing or foam assistance in fractured zonesMust be determined based on formation data
TransportFlatbed load capacity, road width and height limits, mast locking, and drilling tool securingWhole machine about 14 T, dimensions about 6.64 × 2.25 × 2.67 m
SitePlatform bearing capacity, leveling, outrigger pads, climbing and wet-slippery risksClimbing reference 21°; soft soil and slopes require separate assessment

Items marked "to be verified" in the table indicate that the information currently available on this site is insufficient to draw a direct conclusion and should be completed during the inquiry and construction organization stages. For example, the matching of specific air compressor displacement with the DTH hammer, the casing scheme for fractured zones, and measured values of site bearing capacity all need to be confirmed with project data.

Conditions to provide together when inquiring

To ensure that equipment configuration and supporting solutions correspond to the actual well location, the following should be provided when inquiring: drilling purpose (domestic water supply, irrigation, industrial or mining area water supply), regional hydrogeological and formation data, target hole depth and design hole diameter, intended drilling method (mud rotary or DTH hammer), access road and site conditions, water, power, and air supply conditions, and whether mud pumps, generators, foam pumps, and other accessories are needed. Without these conditions, only conditional recommendations can be given within the equipment capability range, and no commitment can be made regarding completed well depth or water yield.