Before starting a medium-deep water well, the most problematic part is often not the drilling itself but the failure to match equipment and site conditions item by item: the design well depth sits right at the equipment limit, the formation requires a DTH hammer but the air compressor displacement is insufficient, or the crawler equipment reaches a village road only to find the ground cannot bear it. If any one item does not match, work stops on site and the plan must be changed.
This article follows the order of items to be settled before startup and breaks the key conditions in the data for a 450 m-class crawler water well rig into a checklist. The checklist is not a fixed template; readers can select according to their project's well depth, formation, and site.
Item 1: Well depth and hole diameter—first see how much margin remains between the target and the equipment limit
The equipment data gives a maximum drilling depth of 450 m and a hole diameter of 105–400 mm. These two values are capability limits; they do not mean that 450 m can be drilled in any formation, nor that a 400 mm hole diameter will still run smoothly in the deep-hole section. Before startup, the design well depth, completed well diameter, well casing, and submersible pump configuration should be reviewed together: if the design well depth is close to 450 m, confirm the equipment's actual construction records and drilling tool configuration in the target formation; if the design well depth is in the 300–400 m range, the capability margin of this rig is relatively clearer.
The same applies to hole diameter: 105–400 mm is a range, and a specific project must settle on a certain hole diameter and matching bit, then check whether the drilling tools, cuttings removal, and air supply can match at that diameter.
Item 2: Formation determines the process, and the process determines the supporting equipment
The data lists the applicable formations as loose formations and rock formations, and gives two process paths: soil, clay, sand, and gravel layers can use mud rotary with wall protection and cuttings carrying; after entering relatively intact rock formations such as limestone, sandstone, and granite, a DTH hammer and bit can be configured for pneumatic DTH drilling. The two paths have different site requirements:

- Mud rotary requires a mud pump, a mud pit or circulation system, and arrangements for disposing of waste mud;
- DTH drilling requires an air compressor matched by pressure and flow; the data gives a working air pressure of 1.2–3.5 MPa and air consumption of 16–55 m³/min, and requires attention to DTH hammer lubrication and bottom-hole cuttings removal.
Therefore, before startup, first make a qualitative judgment of which type of formation the main hole sections belong to: when the upper overburden is thick, generally establish a stable borehole wall first and then enter the rock formation to switch processes; broken zones, fracture-developed sections, and strong water inflow sections will change cuttings removal and borehole wall conditions. The data mentions that foam or casing may be considered, and the specific plan should be determined according to the actual conditions of the hole section. If the project's formation data is insufficient, this item is a matter to be verified and cannot be inferred from equipment parameters.
Item 3: Air and water supply—verify separately according to the process path
During pneumatic DTH drilling, the air compressor's pressure and displacement must both be satisfied. The data explains that when the hole diameter increases, the rock becomes harder, or the altitude rises, the displacement requirement is higher, so selecting an air compressor cannot rely only on the pressure value. For mud rotary, the mud pump selection and smooth circulation must be settled; the data mentions that the mud pump can be selected according to the project formation and construction method.
Sites lacking a stable power supply may also need a generator, and the foam pump in the data corresponds to hole sections with severe air leakage. These are supporting conditions and should be configured according to the main working conditions, avoiding piling on equipment for infrequently used hole sections.
| Process path | Supporting equipment to be settled | Corresponding conditions in the data |
|---|---|---|
| Mud rotary | Mud pump, circulation and hole cleaning arrangements | Suitable for soil, clay, sand, and gravel layers |
| Pneumatic DTH | Air compressor pressure and displacement, DTH hammer lubrication | 1.2–3.5 MPa, 16–55 m³/min |
| Air-leakage or broken hole sections | Auxiliary measures such as foam or casing | Listed in the data as directions to consider; to be confirmed by hole section |
Item 4: Drilling tools and lifting capacity—verify tripping and casing operations
This model supports 6 m drill pipes, with recommended drill pipe diameters of 89 / 102 mm; the 20 T lifting force is used for routine tripping of 450 m-class drill pipes, DTH hammer recovery, and some casing operations. What must be verified before startup: whether the project's drill pipe specifications fall within the recommended range, the drill string load after the weight of a single drill pipe is superimposed with the hole depth, and whether heavier accessories require the auxiliary winch.

The auxiliary winch has a standard lifting force of 1.1 T, with 2.5 T optional. If the DTH hammer, casing, or other accessories on site are heavy, the auxiliary winch configuration will affect the manual handling intensity and should be raised at the equipment ordering stage.
Item 5: Rotation and power—judge working conditions by hole diameter and resistance
The data gives dual-condition torque of 9000 / 4500 N·m, corresponding to maximum rotation speeds of 90 / 180 r/min; the power is 92 kW. The high-torque, low-speed state is more suitable for large-diameter, hard-rock, or high-resistance hole sections, while the higher-speed state is suitable for stages with relatively lower resistance. Before startup, combine the target hole diameter and expected rock hardness to judge which working condition the main hole sections fall into, rather than understanding the dual conditions as a two-speed gearbox.
The 92 kW power must simultaneously handle rotation, feed, crawler travel, and auxiliary hydraulic functions. The data reminds that during continuous hard-rock construction, engine cooling and air filter maintenance should be strengthened; this is an operating condition and does not constitute an efficiency judgment for any specific site.
Item 6: Site access and relocation—verify by weight, dimensions, and road conditions
The overall weight is about 8.5 T, the overall dimensions are about 5.85 × 1.8 × 2.4 m, the travel speed is about 2.5 km/h, and the maximum climbing angle reference is 21°. The crawler structure is suitable for village roads, gravel ground, and generally uneven ground, but before relocation, confirm road width, bridge and culvert load capacity, slope conditions, and soft, wet areas; movement on soft ground should be cautious.

The hydraulic outrigger stroke is 1.6 m, which can help level the equipment and provide stable support on mildly uneven sites; on soft ground, pads should be used to prevent outrigger settlement. Medium-deep hole construction has a long cycle, and outrigger and site stability directly affect hole deviation and mast loading.
Pre-start checklist and items to be confirmed
- Whether the design well depth, completed well diameter, well casing, and submersible pump configuration are clear;
- Whether the formation stratification data is sufficient to determine the hole sections for switching between mud rotary and DTH drilling;
- Whether there are selection conclusions for air compressor pressure and displacement, mud pump, and generator;
- Whether the drill pipe diameter, drill string weight, and lifting force match, and whether the auxiliary winch needs upgrading;
- Site access roads, site bearing capacity, slope, and outrigger pad arrangements;
- Local hydrogeological data, main aquifer locations, and water shut-off and filter pipe design.
It should be noted that the maximum drilling depth, drilling efficiency, and well completion results are subject to site working conditions; the reference drilling efficiency given in the data is 10–35 m/h, affected by formation, drilling tools, air compressor, and operation, and cannot be taken as a commitment for a specific project. If the project involves complete core sampling, a dedicated core drilling rig should be used instead; a water well rig cannot replace coring purposes.
When requesting a quotation, it is recommended to provide: drilling purpose (irrigation, water supply, aquaculture, or hydrogeological survey), design well depth and hole diameter, formation data, proposed drilling method, number of holes and relocation distance, site access roads and site conditions, water, power, and air supply conditions, and whether a mud pump or air compressor is needed. The more complete the information, the more grounded the discussion of equipment configuration and supporting scope will be.