Most small water well rig projects are located beside village roads, in orchards or next to livestock farms, where the ground is uneven and borehole positions are scattered, and the equipment itself is not heavy. In such projects, the most common pre-start problem is not insufficient machine capability but a reversed preparation sequence: the equipment is agreed first, then it is discovered that the road cannot be accessed; the well site is fixed first, then it is discovered that the well casing and drill pipe specifications do not match. Using a 180 m class crawler water well rig as the subject, the following arranges pre-start preparation items in order of priority for reference in small rural water supply and farmland irrigation projects.
1. Determine the well site and target first, then discuss equipment
The well site is the starting point of the entire preparation process. It determines where the equipment must go, what kind of site is needed, and also the approximate range of borehole diameter and completed well depth. According to the model specifications, its borehole diameter covers 90–230 mm, with a maximum drilling depth of 180 m. These two figures can only be understood as capability limits; the actual completed well depth still depends on the local groundwater level, aquifer position, hole diameter and construction process, and the nominal value cannot be directly treated as the completed depth of every well.
Information that must be confirmed together when the well site is determined includes: water use purpose (domestic water, irrigation, livestock), expected well casing diameter and submersible pump specifications, and the depth and aquifer conditions of nearby existing wells. If the hole diameter is too small, it will restrict the installation of well casing and pumps; if too large, it will impose higher requirements on drilling and cuttings removal. Therefore, the hole diameter should be determined together with the water demand at the well site stage.
2. Verify the site and access roads before the equipment
The specifications show that the machine has an overall weight of about 1.8 t, overall dimensions of about 3000 × 1300 × 1700 mm, and a travel speed of 2.5 km/h, making it suitable for transfer between sites using small transport vehicles. This set of data highlights the preparation priorities: village road width, turning radius, bridge and culvert load capacity, and the roadbed condition of field dirt roads must all be inspected on site before the equipment is mobilized, and it cannot be judged merely from dimension figures whether it can pass.

Workface preparation includes the space required for raising and lowering the mast, the operating positions for placing drill pipes and tripping in and out, and the temporary storage area for mud or cuttings. The 1.5 m mast is a relatively low working height on this model and is suitable for courtyards and small sites, but the frequency of drill pipe changes will be higher than on long-stroke models; this point requires reserving space for drill pipe turnover during site layout, rather than squeezing it in after work starts.
3. Select drilling tools and circulation support according to hole diameter and formation
The machine can be equipped with drill pipes of three diameters: 50 mm, 60 mm and 76 mm, and drill pipe lengths of 1.5 m and 2.0 m. The drill pipe diameter must be considered together with the hole diameter and bit type, while the length is related to the mast stroke and the number of pipe connections. During the preparation stage, it should be clarified which drill pipe grade is selected, and corresponding joints and wear parts should be prepared accordingly to avoid temporary reconfiguration on site.
The working pressure specifications are marked as 1.7–3.0 MPa, rotation speed 40–70 rpm, and lifting force 16 T. These values are operating parameter ranges, not commitments to construction results. Soil layers, clay, sand layers and gravel layers may collapse, shrink or bury the drill; during preparation, the hole stabilization method and cuttings removal method should be confirmed. If drill lifting resistance in the hole is abnormal, the formation and borehole wall condition should be assessed first, and it is not advisable to rely solely on maximum lifting force to pull hard.

4. Bring power, personnel and consumables to the site together
The machine is equipped with a 28 HP diesel engine driving the hydraulic system, rotation and travel, and does not rely on a fixed power grid, making it suitable for remote agricultural sites. Preparation items should therefore include fuel reserves, engine oil and coolant checks, air filter spare parts, and daily inspections according to the manual. For continuous operation, it should be made clear before start-up who is responsible for the inspection items.
In terms of personnel, at minimum the division of labor for operation, tripping assistance and recording should be clarified. Well depth, hole diameter, formation changes and cuttings conditions should be recorded item by item; these records are both the basis for the day's construction and the basis for tracing back if downhole problems occur.
5. Information to prepare before requesting a quotation
Looking at the preparation sequence in reverse, the more specific the conditions that can be provided during quotation, the easier it is to match the equipment plan. The following contents are recommended:

- Drilling purpose and expected well depth; it is advisable to note whether it is for domestic water, irrigation or livestock water;
- Target hole diameter and specifications of well casing and submersible pump;
- Known formation conditions, including the distribution and alternation of soil layers, gravel layers and weathered rock;
- Number and distribution of well sites, and whether frequent relocation is required;
- Access road and workface conditions, and whether transport vehicles can reach near the well site;
- On-site water, electricity and air supply conditions, and whether self-provided power is needed;
- Support requirements, including drill pipe specifications, bit type and quantity of wear parts.
6. Which judgments should still be left to the site
It should be noted that the specifications provide equipment capability and configuration, and do not constitute a conclusion on the well completion effect, water yield or drilling efficiency of any specific project. For projects dominated by complete high-hardness rock layers, or those constructed near the maximum drilling depth for a long time, whether the drilling tools, power and equipment class match should be rechecked during the model selection stage, rather than assuming that this model can cover them. The groundwater level, aquifer thickness and borehole wall stability at the well site can only serve as the basis for the well completion plan after confirmation through on-site survey or existing well data.
By proceeding in the above order, small water well projects can align the well site, site, drilling tools and power lines before equipment mobilization, reducing the possibility of rework and adjustment after arrival.