Slope anchoring holes, foundation pre-drilling holes, and short pile pre-drilling are not deep, but hard rock brings many troubles: narrow platforms, varied hole directions, hard rock, and abundant rock dust. Once the process is disordered, the machine may be in place but drilling will not proceed smoothly. This article does not discuss deep well capability; it only breaks this type of shallow-hole operation into several sequential steps, and then compares them with data from a 30-meter-class crawler hydraulic DTH drill rig to see which steps it can handle and which conditions must be established on site first.
First, answer the core question: why do these shallow holes depend more on process than drilling depth?
Slope anchor bolt holes, anchor cable holes, drainage holes, and foundation pre-drilling holes usually have target depths measured in meters, with hole diameters ranging from tens of millimeters to over two hundred millimeters, and the drilling target is mostly medium-to-high hardness rock. Unlike deep wells, the construction obstacles for these hole positions are concentrated at the front end: whether the equipment can get close to the platform, whether the drill boom can be positioned to the design hole direction, whether the air supply can support continuous operation of the DTH hammer, and whether the cuttings at the hole collar can be removed in time. If any of these is not implemented, the drilling itself will be interrupted.
Therefore, when arranging the process, first determine "where to drill and in which direction," then determine "with what air volume and drilling tools to drill," and finally "how to clean and move after drilling." Drilling depth is only one constraint, not the sole basis for determining machine size.
Step 1: Positioning and transfer—the crawler chassis must first pass the site test
Slope operation platforms are often not leveled ground; they may be compacted soil, gravel bedding, or paved surfaces. According to the data, this model uses an engineering rubber crawler chassis, with an overall weight of about 2500 kg, dimensions of about 3200 × 1200 × 1850 mm, and a width of about 1.2 m. The judgment points corresponding to this size are: whether it can enter the work face from the construction access road, whether there is space for support pads at the platform edge, and whether the turning radius conflicts with enclosures or the slope toe.

Rubber tracks have an adhesion advantage on gravel, compacted soil, and generally uneven ground, and are relatively friendly to finished paved surfaces and concrete floors, making them suitable for urban construction and short-distance transfers within plant areas. However, this does not change the basic prerequisites for slope operations: the platform must be stable, rockfall and edge risks must be addressed first, and the equipment should not operate directly on unstable slopes. Platform bearing capacity, groundwater lines, and underground pipelines are items that must be verified before mobilization; the data cannot replace on-site judgment.
Step 2: Hole direction and attitude—swing angle and tilt adjustment each handle one part
The hole direction of anchoring holes is determined by design, including vertical holes, inclined holes, and some lateral holes. The data gives a swing angle range of 18–180° and notes that it has a tilt adjustment function, but the original data does not give the specific numerical range of the tilt angle. This means that the usability judgment must be made at two levels: the swing angle range indicates that the equipment can cover a large attitude range; whether the design angle of a specific project falls within the adjustable range must be based on the final production configuration and technical confirmation documents, and it cannot be assumed that any angle can be constructed solely because it "has tilt adjustment."
In terms of process, attitude adjustment should be arranged before drilling tool installation and set in place at one time provided the ground bearing capacity is sufficient, to avoid repeatedly changing the angle during drilling. After the hole collar position is determined, check the slide frame stroke—the data gives a slide frame stroke of 3.2 m and an effective stroke of 2.2 m, which determines the advancement length of a single drill rod and the arrangement of rod connection positions.
Step 3: Power and air supply for hard rock drilling—two sets of data must be paired
This model has a maximum rotary torque of 3500 N·m, a drilling diameter of 76–280 mm, and is suitable for rock hardness of about f=8–24, covering medium-to-high hardness rock such as limestone, granite, sandstone, and basalt. Torque is matched with hole diameter and rock properties: when the hole diameter increases or rock abrasiveness increases, rotational resistance rises, and feed and impact parameters must also be matched accordingly.

What really determines the pace of DTH drilling is compressed air. The data gives a reference air consumption of about 8 m³/min, while noting that the original table marked it as 8 m²/min, which is understood as m³/min according to the common unit of compressed air flow; the final value should be confirmed by formal technical documents. The pressure level, continuous air supply capacity, and pipeline pressure drop of the air compressor directly affect the impact effect of the DTH hammer; when the air supply is insufficient, the impact weakens, cuttings removal slows down, and drilling becomes noticeably sluggish. The matching air compressor is independent equipment outside this machine, and its selection must be checked item by item according to the DTH hammer specifications and hole diameter, rather than looking only at the machine itself.
The feed speed of 53 m/min in the data is the rapid movement speed of the feed mechanism, used for non-drilling actions such as power head return and drill rod handling, and cannot be taken as the actual rock penetration rate. Actual penetration is jointly affected by rock hardness, hole diameter, DTH hammer specifications, air compressor capacity, and bit wear; this article does not make efficiency commitments.
Step 4: Hole cleaning and cuttings removal—incorporate dust and hole wall issues into the process
DTH drilling relies on compressed air to discharge rock cuttings, and whether cuttings return is continuous is a direct signal for judging conditions inside the hole. If dust is obvious in dry hard rock, a dust collector or water mist suppression system can be configured according to the project; operators should be equipped with goggles, dust masks, and hearing protection according to local construction regulations.

Ground conditions greatly affect the process sequence. The upper weathered rock and soil-rock mixed layers are prone to unstable hole walls; the feed speed should be reduced, and casing or starting drilling tools should be used as needed; after entering intact rock, the parameters can then be adjusted. In fissures and broken zones, prevent block falling, air leakage, and sticking; do not feed too fast and maintain continuous hole cleaning. If the high-pressure air line pressure is abnormal or cuttings return suddenly stops, stop drilling and check first.
Application boundaries: what type of holes does the 30-meter-class positioning correspond to?
This model has a maximum drilling depth of 30 m and is positioned for engineering rock holes, not deep water well equipment. Water supply wells of 200 m, 300 m, or more require dedicated water well drilling rigs, and a 30-meter-class DTH drill rig cannot be used as deep well equipment. Conversely, slope anchoring, equipment foundations, guardrail piles, short piles and hard rock foundation pre-drilling, quarry bench holes, and auxiliary engineering holes are typical uses listed in its data. The data also mentions that it can be used for short pile pre-drilling and can be optionally equipped with corresponding piling or pre-drilling attachments, but the specific matching relationship of the attachments must be confirmed according to the project.
Several conditions to put on paper before starting work
- Hole parameters: purpose (anchor bolt, anchor cable, drainage, foundation pre-drilling), target hole depth, hole diameter range, design hole direction and tilt angle.
- Ground data: lithology, hardness and integrity description, location of weathered layers and broken zones, used to determine whether casing is needed.
- Site conditions: platform size and bearing capacity, access road, turning space, underground pipelines, and surrounding structures.
- Air supply matching: pressure and flow of the proposed air compressor, pipeline length and pressure drop, and interface specifications of the DTH hammer and bit.
- Environmental protection and protection: whether to equip a dust collector or water mist suppression, and local construction requirements for dust and noise.
- Items to be confirmed: specific tilt adjustment range, formal wording of the 8 m³/min air consumption, and matching relationship of short pile pre-drilling attachments.
Provide the above information together when requesting a quotation so that the supplier can judge whether this model falls within the project conditions and give matching recommendations for the air compressor, drilling tools, and attachments; with only the two words "30 meters" and "hard rock," it is impossible to confirm whether holes can be successfully completed on site.