Tunnel size limits before drilling depth: underground coring split plan

Date:2026-11-14 08:36:56Views:14

When making preliminary plans for underground coring projects, the first thing that is easily put on the table is the drilling depth - such as how many meters the ore body extension should be controlled, and whether BQ or NQ specifications should be used. But what really determines whether the equipment can be put on the ground is often the more advanced step: how the drilling rig enters the tunnel. The tunnel's clear width, clear height, turning radius, slope of the inclined shaft, cage cavity size and rail transportation capacity are too tight, and the whole machine may not be able to reach the drilling site. This article discusses this sequence issue: the transportation channel is cleared first, and then the drilling depth indicator is meaningful.

Should the complete machine be put in first, or should it be disassembled and reassembled?

The underground drilling site is different from the surface hole location. Large equipment can be driven directly into the surface, while underground needs to pass through shafts, inclined shafts or tunnel systems. When the complete machine solution is limited in transportation channels, there are usually two options: switch to a smaller level complete machine, or choose equipment that can be split into modules and reassembled at the drilling site. The former may sacrifice drilling capacity, while the latter tests the installation organization and drilling site layout.

The basis for judgment can be roughly divided into three groups: first, whether the single size and weight of the transport unit falls within the lifting capacity of the cage, mine car or inclined shaft; second, whether each unit can be lifted, assembled and put into position within the limited space of the drilling site; third, whether the assembled equipment can cover the designed hole depth, hole diameter and drilling direction. After these three sets of conditions are confirmed, it will be of practical significance to discuss the specific model.

Which processes correspond to modular transportation?

Take this underground electric fully hydraulic core drilling rig in the data as an example. Its modular design is based on separately transporting the power station, feed mechanism, drilling rig chassis, fuel tank and operating unit, and then completing the combined installation at the underground drilling site. The reference weight of the main modules given in the data is: power station single module 240/270 kg, main engine feed mechanism 130 kg, drilling rig chassis 120 kg, fuel tank unit 120 kg, operating unit 90 kg (another parameter table is marked as 130 kg, which needs to be subject to official technical confirmation data).

Tunnel size limits before drilling depth: underground coring split plan

These values ​​cannot be directly equated to "any cage can pass", but they can be used as the starting point for calculating the transportation plan: compare the heaviest module with the ability of on-site lifting and translation tools, compare the longest module with the inner cavity of the cage and the turns of the tunnel, and then decide how many batches to go down the well and where to temporarily store and assemble.

The drilling depth indicator should be viewed together with the drilling direction.

Downhole drilling is not in one direction. From the existing tunnel to the depth verification, to the side control of the ore body, and to the upward verification of the roof, the stress on the drill string and the construction organization are different. The reference drilling depths given in the data are: BQ 920 m, NQ 800 m, and HQ 380 m in the 90° direction; BQ 600 m, NQ 400 m, and HQ 200 m in the 0° direction; BQ 350 m, NQ 200 m, and HQ 150 m in the -90° direction.

This set of data shows that NQ 800 m cannot be understood independently of the drilling direction. The reference drilling depth of horizontal holes and upward holes is significantly lower than that of downward holes. If you only use "NQ 800 meters" to correspond to the project hole depth when selecting, it is easy to have insufficient capabilities after the angle changes. Different mines may have different definitions of the positive and negative signs of angles, which should be checked with the on-site installation direction and design drawings before formal construction.

Tunnel size limits before drilling depth: underground coring split plan

Electricity conditions and cooling water are facilities that need to be confirmed before entering the site.

The equipment is powered by an electric motor and is configured as 22 kW × 3 or 30 kW × 2. The main system flow rate is 200 L/min and the pressure is 210 bar. The motor solution does not produce combustion exhaust gas in underground drilling sites and is suitable for mines with stable power supply systems. However, the electrical plan must be confirmed item by item based on mine voltage, frequency, cable length and starting method.

There are two other items that are easy to be dealt with later: one is explosion protection. Ordinary motor configurations cannot be directly regarded as explosion-proof configurations. In coal mines, gas mines or environments with combustible dust, the explosion-proof levels of motors, electric control boxes, cables and protection systems should be confirmed according to local mine safety regulations. They must not be directly used in areas with explosion-proof requirements without confirmation. The second is cooling water. The hydraulic oil tank has a capacity of 100 L and is water-cooled. The underground air flow is limited. Water cooling helps control the oil temperature, but it is necessary to ensure that the cooling water supply and heat exchanger are smooth. When the water quality is poor, the impact of cleaning and scaling on heat dissipation must also be considered.

Field conditions for hole operation and drill pipe clamping

The underground drilling site has a compact space, and the drill pipe shackles and hole opening operations are concentrated. According to the data, the maximum applicable drill pipe size of the drill pipe holder is 108 mm, the through hole is 128 mm, and the clamping force is 80 kN. This type of configuration corresponds to the stability requirements during repeated operations of the orifice, but the wear of the clamping block and the hydraulic pressure still need to be checked regularly during construction. On-site confirmation cannot be omitted just because the parameters are nominal.

Tunnel size limits before drilling depth: underground coring split plan

The feed mechanism is driven by a hydraulic cylinder with a stroke of 1800 mm, a propulsion force of 65 kN, a lifting force of 130 kN, and a rapid moving speed of 0.9 m/s; the power head is a hydraulic top drive with a rotation speed of 0–1500 rpm and a torque of 600–1480 N·m. The drill string stress states of horizontal holes, downward holes and upward holes are different. The feed and pullback parameters should be adjusted based on the hole depth, friction and the conditions inside the hole, rather than copying the reference value in a certain direction.

Boundary between fracture zone and fault gouge conditions

When encountering fault mud, breccia or strong fracture zone, the data recommends shortening the number of rounds, reducing the advance and observing changes in return water. If necessary, use casing, adjust the flushing fluid or perform treatment in sections. The focus of this type of working conditions is the stability of the hole wall and the effective recovery rate of the core, rather than simply chasing footage. The equipment can be equipped with an optional 120 series high-pressure plunger pump, with a maximum flow rate of 120 L/min and a maximum pressure of 70 bar. It is used for flushing and some special circulation conditions; whether to configure it must be confirmed in conjunction with the in-hole flushing and circulation design.

Checklist before purchasing

  • Transport channel: cage inner cavity size, inclined shaft slope and lifting capacity, tunnel's narrowest point and turning radius, drilling site lifting tools.
  • Drilling design: target hole depth, drilling direction and angle, BQ/NQ/HQ specification combination, whether it can also be used as advance geological drilling.
  • Electrical conditions: mine voltage and frequency, cable laying length, starting method, whether explosion-proof configuration is required.
  • Cooling and hydraulics: cooling water source and quality, heat exchanger cleaning conditions, hydraulic oil cleanliness management.
  • Drilling site layout: bottom frame fixation method, roof and side support inspection, cable and hose avoidance transportation channels.
  • Supply confirmation: The weight of the operating unit is 130 kg and 90 kg respectively in the two documents. The final configuration and actual weight are subject to the official technical confirmation document.

When making an inquiry, it is recommended to provide the supplier with the drilling purpose, stratigraphic data, target hole depth and diameter, drilling direction, tunnel transportation conditions, power supply and cooling water conditions, whether explosion protection is required, and the specifications of supporting drilling tools, so that the other party can judge whether the split plan is suitable, instead of just reporting a drilling depth number.