ShanBo
Location:Home>News Center

-News Center-

Site and Support Conditions for Truck-Mounted Direct-Mast Drills Before Deep Water Well Spudding

Date:2026-11-14 10:00:24Views:20

Before spudding a deep water well project, one of the most common situations is this: the equipment capability already matches the target well depth, but site preparation is still stuck at the stage of "find a flat piece of ground and it can be done." For equipment such as a 1000 m-class truck-mounted direct-mast water well drill with a total weight of about 26 T and a transport height of about 4.23 m, the site and support conditions before spudding are not ancillary matters; they are preconditions that determine whether the equipment can enter the site smoothly and whether the drill site can operate continuously. The following lists the items that need to be checked one by one across four lines: transport access, drill site layout, drilling process support, and well completion support.

1、Transport Access: Check the Roads First, Then Discuss Equipment Capability

The basic consideration of the truck-mounted direct-mast structure is to allow the drilling system to move with the vehicle and reduce repeated loading and unloading by flatbed truck. But this does not mean that any road condition can be passed directly. The overall transport dimensions are about 10.8 × 2.5 × 4.23 m, and the weight is about 26 T. At minimum, the following items should be checked before entry:

  • Height limits and overhead obstacles: The 4.23 m transport height needs to be compared with the actual clearances of bridges, tunnels, overhead lines, factory gate openings, and tree canopies along the route; it cannot be estimated only by the height of ordinary trucks.
  • Road bearing capacity and slope: The heavy-duty chassis has requirements for subgrade bearing capacity, turning radius, and longitudinal slope. For village roads, field ridges, and temporary access roads, it is necessary to judge in advance whether they can bear the passage of the complete machine.
  • Entry route and spacing between drill points: For projects with scattered drill points such as mining areas, farms, and industrial parks, the advantage of the truck-mounted chassis lies in road transfer, but the premise is that there are actually passable roads between the drill points, rather than construction access roads that need to be opened separately.
  • On-site turning and parking space: After the vehicle enters the site, it needs to complete positioning, outrigger deployment, and mast raising, so sufficient operating space must be left around the drill site.

These conditions cannot be judged by equipment parameters alone. Road height limits, bridge bearing capacity, and turning conditions should be based on on-site survey results and, when necessary, confirmed with the road management authority.

2、Drill Site Layout: Platform Bearing Capacity and Wellhead Position Must Be Determined First

After the truck-mounted direct-mast drill is positioned at the hole location, the weight of the complete machine and the alternating loads during drilling will be transmitted to the drill site ground. Before spudding, confirm:

Site and Support Conditions for Truck-Mounted Direct-Mast Drills Before Deep Water Well Spudding

  • Whether the drill site platform is level and compacted, and whether it can bear the static and dynamic loads of the complete machine and supporting equipment;
  • The relationship between the wellhead position and the vehicle parking direction, and whether it is convenient for drill pipe raising and lowering, casing running, and auxiliary winch operation;
  • Whether the positions of the mud pit, clean water pit, cuttings stacking area, and material stacking area are separated from the drill site working face;
  • Lighting layout, personnel access routes, and emergency evacuation routes during night construction;
  • The drainage direction of the drill site, to avoid mud and return water accumulating in the platform and affecting chassis stability.

This model is equipped with a 4 T large auxiliary winch and a 3 T small auxiliary winch, which can be used for handling DTH hammers, drill pipes, casing, air hoses, and on-site accessories. During drill site layout, the winch working radius and lifting path should also be considered to avoid crossing vehicle access routes.

3、Drilling Process Support: Implement Air Supply, Mud, and Drilling Tools by Formation Section

A 1000 m-class deep well often has to pass through loose overburden, weathered rock, fractured zones, and intact rock formations. Different hole sections require different process support. Before spudding, preparations should be made by design hole depth and expected formation sections:

Hole Section/FormationDrilling Methods to ConsiderSupport to Be Implemented Before Spudding
Upper loose layer, clay, sand layer, gravel layerMud rotary drilling, casing, or other hole stabilization methodsMud materials and mixing capacity, casing specifications and quantity, mud circulation and purification conditions
Intact hard rock (limestone, sandstone, granite, etc.)Medium- to high-pressure DTH drillingAir compressor pressure and displacement, DTH hammer specifications, bit condition, hole cleaning and cuttings return conditions
Fractured zones, weathered rock, and mixed formationsSwitch to DTH after stabilizing the hole with mud or casingHole wall stabilization measures, contingency plans for falling blocks and hole shrinkage, adjustment plans for penetration parameters
Strong aquifers and high-inflow hole sectionsAdjust air supply and hole cleaning methods according to water inflowRecords of water-bearing layer depth, design of screen pipes and water shutoff sections, selection of completion pump type

The equipment data gives a recommended DTH working pressure of 1.65–8 MPa and air consumption of 16–96 m³/min. This range indicates that the complete machine can adapt to DTH hammers of different specifications, but it cannot be used to directly determine the air compressor configuration for a specific project. Actual selection needs to be comprehensively judged based on DTH hammer specifications, hole diameter, hole depth, altitude, and rock hardness; the continuous air supply capacity of the air compressor, pipeline pressure drop, and high-altitude environmental correction should all be confirmed before spudding.

In terms of drilling tools, this model has a feed stroke of 7 m, can use 3 m or 6 m drill pipes, and the recommended drill pipe diameter is 114 mm. 6 m drill pipes are suitable for long-cycle deep hole construction to reduce the number of pipe connections; 3 m drill pipes are more suitable for sites with limited space, transport, or manual operation conditions. Drill pipe specifications, joint types, and quantity should be separately checked according to the design hole depth and process arrangement.

Site and Support Conditions for Truck-Mounted Direct-Mast Drills Before Deep Water Well Spudding

4、Well Completion Support: Hole Diameter, Well Casing, and Pump Type Must Be Determined Together

This model has a drilling diameter range of 105–800 mm, covering conventional water wells to large-diameter water supply wells. The selection of hole diameter cannot be based only on the upper limit of equipment capability; it must be determined in combination with expected water yield, well casing size, pump type, and completion structure. Increasing the hole diameter simultaneously increases drilling tool load, air compressor demand, casing weight, and hole-forming difficulty, and these effects will be amplified at a hole depth of 1000 m-class.

Well completion support to be implemented before spudding includes:

  • The depth and thickness of the target aquifer, and the expected position of the main water-producing layer;
  • The material, diameter, running depth, and connection method of the well casing;
  • The position of the screen section, wire wrapping specifications, and design of the water shutoff section;
  • The completion pump type, head, and flow rate, matched with well diameter and well depth;
  • Whether hydrogeological investigation and water quality evaluation have been completed, and whether the target aquifer has been confirmed.

The maximum nominal drilling depth of 1000 m is an equipment capability parameter. It does not mean that every well must be drilled to that depth, nor does it mean that this depth can be achieved under any formation conditions. The actual completion depth should be determined by hydrogeological conditions and water supply objectives.

5、Power and On-Site Support: Supporting Conditions Behind the 194 kW Diesel Power

This model is equipped with a 194 kW diesel engine, which provides power for rotation, feed, winch, and auxiliary systems. During long-term deep hole and hard rock construction, the continuous operation of the power system depends on on-site support:

Site and Support Conditions for Truck-Mounted Direct-Mast Drills Before Deep Water Well Spudding

  • Fuel reserve and replenishment methods; remote projects need to plan fuel transportation in advance;
  • Maintenance conditions for engine cooling, air filtration, and the fuel system; sites with heavy dust need to increase the frequency of filter element and radiator cleaning;
  • Oil inspection and contamination control for the hydraulic system;
  • The specifications, length, and connection method of high-pressure air hoses, as well as interface matching with the air compressor.

If the project is located in an arid mining area or a remote agricultural site, pneumatic DTH drilling has a lower dependence on large amounts of mud water, which is a favorable process condition, but the fuel consumption and maintenance requirements of the air compressor also need to be included in the on-site support plan.

6、Project Information to Prepare Before Inquiry

Before communicating with the equipment supplier, organizing the following information clearly will help determine whether this model matches the project conditions:

  • Drilling purpose: deep water well, agricultural irrigation, industrial water supply, mine dewatering, or geothermal investigation;
  • Expected formation column: type and thickness of upper overburden, bedrock type, fractured zones, and aquifer positions;
  • Target hole depth and hole diameter, and whether construction is by diameter sections;
  • Proposed drilling method: mud rotary, DTH, or sectional combination;
  • Height limits, width limits, bearing capacity, and turning conditions of the access road;
  • Drill site platform dimensions, bearing capacity, and water and power supply conditions;
  • Supporting requirements for air compressors, drill pipes, casing, well casing, and screen pipes;
  • Completion pump type and expected water yield requirements.

Among the above conditions, any item lacking measured or design basis should not be concluded directly before spudding. Equipment capability is the starting point for selection, while site conditions and the support plan are the actual constraints on whether a deep water well project can proceed as planned.